We have received an update from Bexar County Commissioner Justin Rodriguez’s office regarding the previously announced estimated $4M project to reconstruct 15 residential streets in Bridgewood with curb and gutter section, 4-foot sidewalks including ADA compliant ramps, and driveway approaches.

The Bexar County Public Works Department will send a notification letter to impacted property owners in the coming weeks.  Construction is expected to begin within the next two months and will take approximately 18 months to complete.  The Project Manager is Bridell Miers who can be contacted at 210-335-0822 or at Bridell.Miers@bexar.org.